nustabet gaming Blueleaf ramps up Laguna floating solar deployment

Updated:2024-12-19 Views:82

MANILA, Philippines — Renewable energy firm Blueleaf Energy Philippines is in talks with contractors for the deployment of a P15-billion floating solar project in Laguna province, an official said.

In a chat with reporters late on Tuesday, Pradeep Gopalakrishnan, senior project manager at Blueleaf, said the group was in discussion with Chinese firms Energy China and Xian Electric for potential deals on engineering, procurement, and construction involving its NKS Solar One.

Article continues after this advertisement

Once inked, Energy China would handle the installation of solar panels, while Xian Electric would focus on the project’s substation, or a facility designed to link lines and cables for transmission and distribution of electricity.

FEATURED STORIES BUSINESS Meralco to refund customers P987M BUSINESS Philippines ranks 2nd in cryptocurrency ownership globally — study BUSINESS What a merger between Nissan, Honda could mean for automakers

READ: Blueleaf Energy to build $1.5-B floating solar facilities in Laguna

“One is Xian Electric, they have 13 years of presence in the Philippines. The other one is Energy China. They are the ones who did the project in Singapore. Basically, if you have been to Singapore, they have done the same floating solar project on the drinking water reservoir. So we are using the same technology here,” he said.

Article continues after this advertisement

“We are almost finalizing these two here,” Gopalakrishnan added.

Article continues after this advertisement

The project is located in Lake Caliraya and Lake Lumot, covering the municipalities of Cavinti, Kalayaan, and Lumban.

Article continues after this advertisement

According to Rafael Macabiog, head of projects at Blueleaf, the NKS Solar One will have a capacity of 220 megawatt-peak (MWp) — its maximum potential output.

He said the company has been gaining progress in securing necessary permits on land use, as well as a service contract and system impact study.

Article continues after this advertisement

The project likewise received the Energy Project of National Significance certification, allowing the company to accelerate regulatory approvals.

Macabiog said they were on track to start construction works by early next year, with its completion and commercial operations eyed by the second quarter of 2026.

Blueleaf is also working on a bigger floating solar project on Laguna Lake, dubbed Bluesolar. With a budget of P66 billion, the project is designed to generate up to 1,300 MWp.

Your subscription could not be saved. Please try again. Your subscription has been successful.

Subscribe to our daily newsletter

house of fun slots casino SIGN ME UP

By providing an email address. I agree to the Terms of Use and acknowledge that I have read the Privacy Policy.

The project, a joint venture between Blueleaf and SunAsia, covers five municipalities in Laguna: Cabuyao, Sta. Rosa, Calamba, Bay, and Victoria.

The S&P Global defines “emerging markets” as countries that have been or are transitioning toward middle- income levels, with good access to global capital markets, deepening domestic capital markets, and global economic relevance based on economic size, population and share in global trade.

Bullion hit an all-time high of $2,704.89 in early Asian trade, up from its previous record of $2,688.83 touched on Thursday.

Groundworks are targeted to begin next year. It is expected to be up and running by 2026.nustabet gaming

READ NEXT The Medical City Clark secures the Prestigious Gold Seal® of ... Mindanao Railway Project Phase 3 study to be completed by Q1 EDITORS' PICK Probe Immigration over Roque's escape from PH – quad comm Vietnam learns lesson about China aggression—everyone’s a target Leyte rallies behind senatorial bet Chavit Singson, lauds his projects Clemency for Mary Jane Veloso still subject to review – Marcos BSP closes 2024 with third rate cut NBA examining increase in 3-point shooting, says Adam Silver MOST READ West PH Sea: PCG monitors 12 Chinese vessels near Bajo de Masinloc Imee Marcos to Bersamin, DBM chief: Don’t let president sign budget Atong Ang confirms relationship with Sunshine Cruz in report Probe Immigration over Roque's escape from PH – quad comm Follow @FMangosingINQ on Twitter --> View comments